QATR.FINAL
28 April 1997
SOFTWARE TEST REPORT
FOR THE
MJY TEAM
SOFTWARE RISK MANAGEMENT WWW SITE
Prepared for:
Dr. Richard Bechtold
SWSE 625
Prepared by:
MJY Team
George Mason University
Approved by:
P. McNeece
MJY Program Manger
RECORD OF REVISIONS
| Revision | Description
| Date |
| QATR 1.0 | Interim Test Report (Build 1)
| March 8, 1997 |
| QATR 2.0 | Interim Test Report (Build 2)
| March 29, 1997 |
| QATR 3.0 | Interim Test Report (Build 3)
| April 12, 1997 |
| QATR 4.0 | Final Build Test Report (Build 4)
| April 28, 1997 |
| QATR - Final | Test Analysis Report
| April 28, 1997 |
TABLE OF CONTENTS
1.0. Introduction 1
2.0. Methodology 1
2.1. Test Template 1
2.2. Test Environment 1
3.0. Test Procedures 1
3.1. Preparation 1
3.2. Initial Link Test Procedure 2
3.3. Rework Test Procedure 2
3.4. Regression Test Procedure 2
4.0 Test Results Summary 2
4.1. Requirements Cross Walk 2
4.2. Interim Builds Summary 2
4.3. Final Build Report 3
5.0 Unresolved (Open) Issues 3
6.0 Recommendations 4
Figures
1 Requirements Cross Walk 4
Appendices
A. QATR 1.0
B. QATR 2.0
C. QATR 3.0
D. QATR 4.0
1.0. Introduction. This report summarizes
the results of the test process performed on the MJY Software
Risk Management Site. The report covers basic test methodology,
checklists (scripts) used during test, test results, and (if applicable)
any remaining unresolved (open) items at product delivery to customer
with proposed corrective action plan and schedule.
2.0. Methodology. The test methodology,
outlined in the Quality Assurance/Test plan, is to test web site
connectivity and functionality, and to verify and validate web
site contents, against SRS requirements. Quality assurance also
used these tests as an opportunity to conduct an informal review
MJY team-generated documents. The test program was synchronized
to the time-phased delivery (build) of increased web site functionality,
and included regression testing to insure continued correct operation
of previously delivered capability. Results of each build test
were disseminated to the program manager, developer, and (if appropriate)
owner(s) of document(s) that requiring rework based on informal
document review.
2.1. Test Template. A test template was
constructed to ensure consistent and systematic test of all site
capabilities. The template layout was patterned on the Build One
website design, then updated as required over the remaining builds.
Each section of the template (website design) was traced back
to its required build delivery as specified in the current MJY
Work Breakdown Schedule (WBS). Furthermore, each deliverable specified
in the WBS was traced back to an originating requirement contained
within the current version of the SRS, and that the SRS could
map each of its requirements to a counterpart deliverable within
the WBS. In this manner, the test team verified that each (build)
deliverable contained all of the contracted functions specified
in the WBS, and that the WBS correctly accounted for all requirements
contained within the SRS.
When completed, the test template served as the interim test report
for that build. The completed template was forwarded to the program
manager and developer for their review and appropriate action.
Any defects or errors noted in the template were transferred to
the QA Defect Tracking Log to ensure follow up action.
2.2. Test environment. All tests were conducted
using a Microsoft Internet Explorer 3.01a browser hosted on a
Micron ClientPro PC platform with a Pentium 166 MHz processor
using a Microsoft Windows 95 operating system. The test platform
was geographically separated from the website host server/network.
3.0. Test Procedures. The following
test activities were followed upon developer notification that
an incremental build was available for test on the MJY website:
3.1. Preparation
3.1.1. Test team reviewed previous test logs and QA Error Tracking
Logs to determine open or reworked items that would need to be
retested.
3.1.2. Test team would peruse the site for modifications to site
layout, and make appropriate corrections or annotations to the
test template.
Using a blank test template, the team would accomplish the following
activities:
3.2. Initial Link Test Procedure. Each new
web page link or control button, whether it links to an internal
portion of the MJY site, or to some other external web site, has
been subjected to the following tests:
3.2.1. Connectivity (that is, can I connect to the indicated URL?)
3.2.2. Readability (that is, can I read the page once connection
is established?);
3.2.3. Navigation at the linked site (that is, can I access or
operate the various functions or capabilities at the "linked"
site.)
3.2.4. Download capability. If the site page has document download
capability, can I download a readable copy of the document?).
Download is marked "N/A" if the site has no download
capability (other than saving display as an HTML file).
3.3. Rework Test Procedure. Test team would
revisit any open items from previous tests to confirm that the
defect or error had been corrected by the development team. Open
items would be subjected to the same paragraph 3.2. test procedures,
and were counted against the regression testing requirement.
3.4. Regression Test Procedure. After performing
the tests outlined in paragraph 3.2. and 3.3., a regression test,
using these same procedures, was accomplished for at least ten
percent of the links from previous builds. Previous test templates
were referenced by the test team so that different links would
be subjected to regression tests.
4.0. Test Results Summary.
4.1. Requirements Cross Walk (Figure 1). Using
this procedure, test team verified that all requirements enumerated
in the requirements matrix were reflected in the SRS. Two requirements,
links to other SWSE 625 sites, and web site area for draft project
papers, were not enumerated in the WBS, although these were delivered
during Build 2. Because the WBS contains the requirements that
will be satisfied by each phased deliverable, test template references
test of each web site section to its corresponding WBS number,
with the two exceptions noted above.
4.2. Interim Builds summary. Test results
for each phased software deliverable are located at Appendices
A through D. A total of seven errors were uncovered by the test
team. With two exceptions, all of the errors occurred at the external
site to which our site was linking. Examples include failure of
the external site to access downloadable information, links at
the external site which had been internally renamed and thus no
longer available, or tertiary links (when an external site linked
to another external site) which were no longer valid. These errors
were not controllable by our development team, and while noted
for possible action after final build testing, did not delay the
development team from moving into the next build. Two errors involving
browser capability was discovered, and will be addressed further
in the final build report.
Defects detected during test were of a QA variety, with the predominant
proportion involving consistency of version number and date between
what was shown on the document cover sheet and what was contained
in the document site index. Disposition of errors and defects
were documented on the QA Error Tracking Log.
4.3. Final Build report. The final build
phase test also served as the customer acceptance test. Paragraph
3.0. build phase test procedures were accomplished for the new
bibliography, "Lessons Learned," and "unique materials"
(term papers) web sections, as well as the software project management
site sectional layout and the new navigation buttons at the top
of each page of the web site. For acceptance purposes, all internal
and (primary) external web site links were rechecked for correct
functionality. (Secondary and tertiary linkages were spot checked;
download capabilities were not checked.) In addition, another
complete bulletin board functionality check was accomplished.
Test results can be found at Appendix D. A summary of acceptance
test results follows:
4.3.1. All external links functioned properly, allowing test team
to connect and correctly navigate within external sites.
4.3.2. All primary internal site links functioned properly, allowing
test team to connect and correctly navigate between site pages.
4.3.3. A previously discovered Build 3 error, concerning the ability
to link to an internal web subpage, continued to manifest itself
during acceptance test. The problem: when navigating to a subsection
of the page, while the correct subsection URL is displayed, the
browser takes you to the top of the selected page. The reader
can scroll down to the correct section, and all other functionality
is not impacted (ie, can download from the section, can navigate
to other links, etc). Further testing showed that the problem
occurs only with the test browser (MS Internet Explorer V3.01a),
and that the problem is intermittent (no particular preconditions
have been identified to cause either consistent successful or
unsuccessful linkage to the targeted section). (This error was
confirmed by a test using the same browser version on a different
test platform, thus ruling out possible platform or platform configuration
induced errors). This error does not occur with those Netscape
browser versions available to the team. Other browsers are not
available to determine their sublink navigation behavior.
4.3.4. Bulletin board functionality was satisfactorily demonstrated
by posting an initial test message, followed by two nested responses.
In each case, the reader could access and read the selected message,
and post a response to same; the bulletin board then correctly
posted the message or response.
5.0. Unresolved (Open) Items:
5.1. Sublink navigation. Further testing using
different browsers is needed to determine whether other browsers
are also affected by this glitch. A different web authoring tool
should also be tried to rule out the possibility of a tool-induced
error. As an interim solution, a warning should be posted on the
web site alerting readers that certain browsers may require they
scroll down the page to reach the correct section.
5.2. Open document review write ups. Time
permitting, recommended corrective action annotated in Quality
Assurance Error Tracking Log and Document Review Reports (see
QATP FINAL, Appendices A-C) should be accomplished by appropriate
development team members. Otherwise, corrections should be accomplished
as part of initial software maintenance activities.
6.0 Recommendations. Based on experience
gained from this test process, the following recommendations are
offerred:
6.1. Web site maintenance: although the internal
site links will remain static, an aggressive monitoring effort
will have to be made to ensure external site links remain valid.
Over this relatively short test period, several tertiary links
(those at external sites) were found to be invalid. The customer
could experience a great deal of user dissatisfaction (as indicated
by steadily decreasing user traffic at the site) should such a
link monitoring program not be put in place. Market research to
find a tool which provides an automatic monitoring or testing
capability of web sites and web site links is recommeneded.
6.2. As an extension of recommendation 1,
acquisition of automated web site test tools for the MJY development
and test teams is recommended. This would facilitate detection
and elimination of any internal site link faults during development
as well as speed up the test process, which must now be manually
accomplished for each link.
FIGURES
| Requirement Description | REQM
| SRS | WBS
|
| Minimum of ten links to other sites
| 3.1 | 3.2.1.
| 4.6.3. |
| Area for MJY draft project documents | 3.2
| 3.2.2. | |
| Bulletin board for user interaction | 3.3
| 3.2.3. | 4.6.2.
|
| Introductory Risk Management Information (novices)
| 3.4 | 3.2.4.
| 4.6.4. |
| Links to other SWSE 625 Sites | 3.5
| 3.2.5 | |
| Links to Web Search Engines and list of suggested Key Words
| 3.6 | 3.2.6
| 4.6.5. |
| Descriptions of five tools for software project management, especially risk
| 3.7 | 3.2.7.
| 4.7.1. |
| Levity Page | 3.8
| 3.2.8. | 4.7.2.
|
| Lessons learned page with links to ten sites
| 3.9 | 3.2.9.
| 4.8.3. |
| MJY Term Paper (Unique Material) page |
3.10 | 3.2.10.
| 4.8.1. |
| Bibliography page, sorted by topic, five links/topic
| 3.11 | 3.2.11.
| 4.8.2. |
Figure 1. Requirements Cross Walk
Software Project Mangagement /
Comments? /
Back /